Course Outlines



  1. How to Install Underground Fuel Storage Tanks and Piping
  2. A Contractor's Guide to UST Closures
  3. OSHA 8 Hour Refresher On-Site Supervisors Hazmat Course for UST Sites
  4. Underground Tank Installers Certification Renewal Course
  5. How to Perform a UST Compliance Inspection
  6. How to Install Shop Fabricated Aboveground Fuel Storage Tanks
  7. UST Operators Training Course
  8. How to Test Cathodic Protection on Underground Storage Tanks
  9. Solutions to New Underground Storage Tank Problems
  10. Underground Storage Tank Technician's Training Course



"How To Install Underground Fuel
Storage Tanks and Piping"
(8 Hours)
  1. Tank Handling (15 min.)
    1. Preparation for handling

  2. Pre-Installation Testing (45 min.)
    1. Above Ground Air Test Procedures
      1. Single Wall Tanks
      2. Double Wall Tanks
    2. Alternative Testing for tanks not covered
            under (2a) above
    3. Precision Tightness Tests

  3. Excavation (30 min.)
    1. OSHA regulations
    2. Size of the excavation
    3. Safety Regulations & Procedures

  4. Anchoring (15 min.)
    1. When to anchor a tank
    2. Methods of anchoring
    3. Maximum burial depth
    4. Anchor design
    5. Concrete pad
    6. deadman anchors

  5. Backfilling (30 min.)
    1. Approved materials
    2. Ballast Tanks
    3. Measuring for deflection in FRP tanks
    4. Amount of backfill needed
    5. Compaction
    6. Filter Fabric

  6. Spill & Overfill Prevention (30 min.)
    1. Spill containment manholes
    2. Float vent valves
    3. Overfill prevention valves
    4. Calculation of overfill prevention device
            from top of the tank

  7. Leak Detection Methods (3.0 Hours)
    1. Federal requirements
    2. Automatic tank guaging
    3. Vapor monitoring
    4. Groundwater monitoring
    5. Interstitial monitoring
    6. Statistical inventory reconciliation
    7. Leak detection for piping

  8. Cathodic Protection (1.25 Hours)
    1. Impressed current systems
    2. Sacrificial anodes
    3. Testing the cathodic protection system
    4. Isolation of the cathodic protection system
    5. Explanation of the anode output in minus DC volts

  9. Piping (1.25 Hours)
    1. Steel Piping
      1. Coating regulations
      2. Types of cathodic protection
      3. Isolation
      4. Types of fitings
      5. Installation procedure
      6. Flex connectors
      7. Piping layout
    2. Fiberglass Piping
      1. Installation procedures
    3. Safety shear valves under dispensers
    4. Minimum pipe slope
    5. Testing the piping system
    6. Vent line requirements
    7. Piping for 100% alcohol fuels

  10. Electrical (15 min.)
    1. Building codes
    2. Seal-offs
    3. Approved wire
    4. Approved Conduit
    5. OSHA lockout/tagout procedures

Top of Page



"A Contractor's Guide to UST Closures"
(8 Hours)
  1. Temporary Closure (30 min.)
    1. Time Frames
    2. Procedures

  2. Permanent Closure (2.0 Hrs.)
    1. Notivication
    2. Safety
    3. Causes and Control of Static Electricity
    4. Proper selection, use and calibration of
      Oxygen & LEL Meters
    5. OSHA Excavation Regulations

  3. Purging the Tank of Flammable Vapors (1 Hr.)
    1. Purging Methods
    1. Eductor Air Mover
    2. Air Diffuser

  4. Inerting the Tank Flammable Vapors (45 min.)
    1. Methods of Inerting
      1. Dry Ice
      2. Compressed Nitrogen & Carbon Dioxide
    2. Improper methods and why they should not be used
      1. Exhaust Gases
      2. Overriching

  5. Cleaning Sludge & Rinsate From the Tank (30 min.)
    1. RCRA Requirements
    2. Cleaning Methods

  6. Closure in Place (30 min.) (30 min.)
    1. Requirements
    2. Methods
    3. Should only be used when Removal is not possible

  7. Closure by Removal (1.5 Hrs.)
    1. Procedure for proper Removal of Tanks
    2. Storage of Used Tanks
    3. Proper Disposal of Removed Tanks
    4. Precautions to take when dismantling tanks that have contained leaded gasoline
    5. The safest method to cut a tank

  8. State Sampling Protocol (1.5 Hrs.)

  9. Piping (1.0 Hrs.)
    1. Federal regulations for iron piping
    2. Common problems found by UST inspectors during compliance inspections
    3. Piping for 100% alcohol fuel

  10. Safety (1.0 Hrs.)
    1. Jobsite safety procedures

  11. Contractor Ethics (15 min.)
Top of Page


"OSHA 8 Hour Annual Refresher
On-Site Supervisors Hazmat Course
For UST Sites"

(8 Hours)

  1. OSHA Lockout/Tagout Regulations (45 min.)
  2. OSHA Excavations Regulations (1.25 Hrs.)
  3. Monitoring INstruments (1.50 Hrs.)
  4. Personal Protective Equipment (30 min.)
  5. Confined Space Entry (1.5 Hrs.)
  6. Site Safety and Health Plan (30 min.)
  7. Medical Surveillance (30 min.)
  8. Decontamination (15 min.)
  9. Hazard Communication / MSDS Sheets (15 min.)
  10. Emergency Response Plan (30 min.)
  11. Hazard Communication (30 min.)
Top of Page


"Underground Tank Installer's
Certification Renewal Course"

Syllabus

(8 Hours)

  1. OSHA Regilations (1.0 hrs.)
    1. Excavations
    2. Lockout/tagout

  2. Backfilling (45 min.)
    1. Requirements for all tanks
    2. Requirements for FRP tands in unstable soil
    3. Compaction for steel tanks
    4. PEI RP/100 Backfill Specs
    5. Actual stories of the consequences of improper backfilling

  3. Overfill Prevention (45 min.)
    1. Approved methods
    2. How to calculate the length of the overfill prevention device from the top of the tank
    3. Pros and Cons of the Alternative method approved by EPA
    4. Examples of where ball float valves are not recommended for overfill prevention
    5. Limitations of other Overfill Prevention Methods

  4. Leak Detection (2.0 Hrs.)
    1. Tanks - Limitations and problems of all approved methods
    2. What is a Precision tightness and when should it be performed
    3. What is third party certification and what does it do
    4. Testing leak detectors
    5. Red jacket test procedure

  5. Field Instruments (15 min.)
    1. Vapor monitoring
    2. Groundwater monitoring

  6. Record Keeping (30 min.)
    1. Leak Detection
    2. Cathodic Protection
    3. Precision tightness tests
    4. Repairs

  7. Upgrading your UST System (30 min.)
    1. What tests must be performed after the upgrade and how often
    2. What have been some of the problems with both methods of upgrade
    3. What are inspectors looking for in an upgraded system

  8. Cathodic Protection (1.0 Hrs.)
    1. How to test a Cathodic Protection System
    2. Proper and improper methods of isolation
    3. How Cathodic Protection works
    4. Problems with Cathodic Protection Systems

  9. Piping (1.0 Hrs.)
    1. Regulations governing flex connectors
    2. Frequent problems found by inspectors during compliance inspections
    3. Piping for 100% Alcohol fuels
    4. Backfill requirements

  10. Safety (15 min.)
    1. Jobsite Safety procedures

  11. Contractor Ethics (15 min.)
Top of Page


"How to Perform a UST
Compliance Inspection"
(8 Hours)

  1. Records Examination (1.0 Hrs.)
    1. Tank Registration
    2. Certification of Installation
    3. Leak Detection
    4. Cathodic Protection
    5. Precision Tightness Tests
    6. Reported spills or releases
    7. Repairs to tanks or piping
    8. Tanks containing hazardous substances
    9. Closed tanks at the site
    10. Aboveground tanks regulated as underground tanks

  2. Leak Detection for Tanks (1.50 Hrs.)
    1. Record Keeping
    2. Third Party Certification
    3. Approved Methods:
      1. Interstitial Monitoring
      2. Automatic tank gauging
      3. Groundwater Monitoring
      4. Vapor Monitoring
      5. Statistical Inventory Reconciliation
      6. Inventory Control and Tank Tightness Testing
      7. Manual Tank Gauging
    4. What to look for during a Physical Inspection

  3. Leak Detection for Piping (0.75 Hrs.)
    1. Suction
      1. Verification
    2. Pressurized
      1. Two methods required
      2. Leak Detector Testing documentation
      3. Satellite Piping
      4. SIR
    3. What to look for during a Physical Inspection

  4. Precision Tightness Tests (1.0 Hrs.)
    1. When should they be performed?
    2. third party Certification
    3. Volumetric
    4. Non-volumetric

  5. Spill and Overfill Prevention (1.0 Hrs.)
    1. Spill containment Manholes
    2. Methods of Overfill Prevention
    3. Calculation of Overfill Prevention Valve Settings
    4. Common compliance violations
    5. Difference between conventional and "alternative methods" of overfill prevention
    6. What to look for during a Physical Inspection

  6. Corrosion Protection (1.5 Hrs.)
    1. New Tanks
      1. Verification of Installation
      2. Cathodically Protected Steel
      3. Fiberglass
      4. Composite
      5. Other types of double wall tanks
    2. Upgraded bear steel tanks
      1. Cathodic Protection added
        1. Documentation of integrity test prior to adding CP
        2. Documentation of "Corrosion Expert" design
      2. Internal Lining
        1. Documentation of precision tightness tests
        2. Internal inspections
        3. Cathodic Protection combined with internal lining

  7. As Built Drawings (0.5 Hrs.)
    1. What they should contain
    2. Illustration

  8. Closed Tanks (1.0 Hrs.)
    1. Are there any temporarily closed tanks at this site?
      1. Have all regulatory requirements been met?
      2. Review all tank documentation
    2. Are there any tanks permanently closed in place at this site?
      1. Have all regulatory requirements been met?
    3. Physical Inspection
      1. Look for vent lines, manholes, capped pipes or other signs a tank may be buried

  9. Vapor Recovery (Optional - when required, 1.0 Hrs.)
    1. Review all documentation:
      1. Testing
      2. Certification
      3. Maintenance
      4. Employee training
    2. Stage I
      1. Physical Inspection of Equipment
    3. Stage II
      1. Physical Inspection

  10. Other Items to Inspect (0.50 Hrs.)
    1. Site Safety Plan
    2. Fire Extinguishers
    3. Manholes
    4. SPCC Plan
    5. Electrical
    6. Oil/Water separator
    7. Proper signing

  11. Facility Inspection Checklist (0.50 Hrs.)
    1. Complete Facility Inspection Checklist
    2. Review all items to be inspected

  12. Regulations (0.25 Hrs.)
    1. Review regulations govening this site
Top of Page


"How to Install Shop Fabricated
Aboveground Fuel Storage Tanks"
(8 Hours)

  1. Pre-Installation Testing, Inspection and Preparation (0.50 Hrs.)
    1. UL Standards
    2. Pre-Installation Air Tests
    3. Tank Location
  2. Tank Installation (0.50 Hrs.)
    1. Maximum Tank Capacity
    2. Foundations
    3. Tank Openings
    4. Anchoring
  3. Pump Installation (0.50 Hrs.)
    1. Suction Pumps
    2. Anti-siphon valves
    3. Remote Pumping systems
    4. Pump elevation lower than tank elevation
  4. Vent Installation (0.50 Hrs.)
    1. Normal vent installation
    2. Emergency vents
  5. Piping and Fittings (0.75 Hrs.)
    1. Aboveground and Underground Piping
    2. Tank filling
    3. Product piping
  6. Cathodic Protection (0.50 Hrs.)
    1. Tankd and components
    2. Vertical tank bottoms
    3. Anode installation of tank bottome
    4. Impressed Current
  7. SPCC Plan (0.50 Hrs.)
    1. Information required
    2. When is it required?
    3. Contingency Plan
  8. Spill Containment (0.75 Hrs.)
    1. Dikes
    2. Dike capacity calculation
    3. Construction materials for a dike
    4. Handling water accumulation
  9. Overfill Prevention (0.50 Hrs.)
    1. Prevention of spills during tank filling
    2. Overfill prevention equipment
  10. Fire Protection and Identification (0.50 Hrs.)
    1. Fire Extinguishers
    2. Alarms
    3. Signs
    4. Identification
  11. Electrical Installation (0.50 Hrs.)
    1. Codes & Regulations
    2. Hazardous Locations
    3. Grounding
    4. Emergency Shut-Off
  12. Other Considerations (0.50 Hrs.)
    1. Product losses
    2. Liability
    3. Local restrictions
  13. Used Oil Tanks (0.50 Hrs.)
    1. Federal used Oil Regulations
  14. Cost Estimates for Aboveground Tanks (0.50 hrs.)
  15. Aboveground Tanks vs. Underground Tanks (0.50 Hrs.)
    1. Should I replace my UST's with AST's?
    2. Cost estimates of AGT vs. UST
Top of Page


"UST Operators Training Course"
Course Outline


I. UST Records Manual
  1. What to do when
    1. NOW
    2. 30 Days
    3. 60 Days
    4. 1 Year
    5. 3 Years
  2. Leak Detection Records
  3. Records of Maintenance & Repairs
  4. Cathodic Protection Records
  5. Precision Tightness Test Records
  6. Tank Registration/Notification & Permits
  7. Other Documents
    1. Warranties
    2. Manufacturers Installation Checklists
    3. Manufacturers Operators Manuals
  8. Site Plan
II. New Employee Training
  1. Employee Emergency and Fire Prevention Plan(OSHA 1910.38)
  2. Informing Employees of Duties and Responsibilities
  3. Informing Employees of Hazards of Working at this site
  4. What to do in case of an Emergency
  5. What to do if an alarm is triggered
  6. Location of and how to use
    1. Fire Extinguisher
    2. Absorbent Pads
    3. Emergency Shut Off Switch
  7. Housekeeping and Maintenance Responsibilities
  8. Accident and Fire Prevention
III. Methods of Leak Detection for Tanks
  1. What to look for during a Physical Inspection
  2. What Records must be maintained for each method
IV. Leak Detection for Piping
  1. Suction Systems
  2. Pressurized Systems
  3. Leak Detector Testing
  4. Satellite Piping
  5. What to look for during a physical inspection
V. Precision Tightness Tests
  1. 5 times when a precision tightness test must be performed
  2. Third Party Certification
  3. Volumetric
  4. Non-Volumetric
VI. Spill and Overfill Prevention
  1. Spill Containment Manholes
  2. Methods of Overfill Prevention
  3. Calculatin of Overfill Prevention Valve settings inside the tank
  4. Common compliance violations
  5. What to look for during a physical inspection
VII. Corrosion Protection
  1. Cathodic Protection Tests
  2. Integrity tests before CP added as a method of upgrade
  3. Documentation needed for tanks that had been upgraded
    1. Adding CP
    2. Internal Lining
VIII. As Built Drawings
  1. What should they contain
  2. Illustration
IX. Closed in Place Tanks on the Site
  1. What are the requirements
  2. Physical inspection
Top of Page


"How to Test Cathodic Protection on Underground Storage Tanks"
Course Outline

8 Credit Hours

1. How Cathodic Protection Works
    1. How Corrosion Works
    2. Types of Corrosion on Underground Storage Tanks
    3. What is Stray Current?
    4. What is Soil Resistivity?
2. Types of Cathodic Protection
    1. How a Galvanic System Works?
    2. What are the Advantages of a Galvanic System?
    3. What are the Disadvantages of a Galvanic System?
    4. How does the Galvanic Chart Work?
    5. How does an Impressed Current System Work?
    6. What are the Advantages of an Impressed Current System?
    7. What are the Disadvantages of an Impressed Current System?
3. Regulations
    1. What are the qualifications of a "Cathodic Protection Tester"?
    2. What are the qualifications of a "Corrosion Expert"?
    3. How often must a Cathodic Protection system be tested?
    4. What are the regulations governing repairs to the UST system?
4. Repairs and Installation of Cathodic Protection Systems
    1. Requirements for STIP3 Tanks
    2. What are the requirements for metallic piping?
    3. What thpes of coating are required on metallic piping?
5. Cathodic Protection Testing Equipment
Classroom demonstration of equipment and calibrations.
    1. What equipment is necessary to test cathodic protection?
    2. What are the specifications for a voltmeter?
    3. What type of ammeter is required?
    4. What type of reference cell is required?
    5. How to calibrate a copper sulfate reference cell?
    6. How to test cathodic protection if there is not a test station?
6. Cathodic Protection Testing Methods
Classroom demonstration
    1. Demonstration of how to perform a structure to soil cathodic protection test.
    2. How to interpret test results?
    3. Demonstration of how to perform an "instant off" test for impressed current systems
    4. How to interpret the results of an "instant off" test
7. Cathodic Protection Test Locations
    1. Placement of copper sulfate reference when testing a galvanic protected tank (STIP3)
    2. Remote electrode placement for STIP3 tanks.
8. Why Cathodic Protection Tests Fail
    1. Discussion of why cathodic protection systems fail
9. How to Test Continuity and Isolation
Classroom demonstration
    1. How to test continuity and isolation on a galvanic system
    2. How to test continuity and isolation on an impressed current system
    3. Demonstration how to perform the "fixed cell-moving ground method"
    4. Interpreting the data from a "fixed cell-moving ground" method
    5. Demonstrate how to perform a "point-to-point" continuity test
    6. How to interpret the data from a "point-to-point" continuity test
10. How to Perform a Current Requirement Test
Classroom demonstration
    1. What is the purpose of a current requirement test?
    2. What material and equipment is required for a current requirement test?
    3. What is the testing procedure for this test?
11. STI Recommended Practice for the Addition of Supplemental Anodes R-972-01
    1. Review and discussion of STI RP for adding supplemental anodes
12. Site Drawings
    1. What information is required on site drawings?
    2. What is the purpose of a site drawing?
    3. Examples of correct site drawings.
13. Glossary of Terms
    1. Explanation and discussion of the terms used in cathodic protection
14. UST Cathodic Protection Evaluation Forms
    1. Review the forms used to record the data collected in performing all of the tests in this course.
Top of Page


"Solutions to New Underground Storage Tank Problems"
Course Outline

8 Credit Hours

1. Revisions to PEI/RP100-2005
    1. Pre-installation testing of compartment tanks
    2. Recommends new requirement for metallic anchor straps
    3. New revisions on ball-float valve installation
    4. New specifications for clearance between piping and electrical conduit, utilities, etc.
    5. Containing releases for submersible pump heads and dispensers
    6. New section on monitoring satellite dispenser piping
2. Revisions to NFPA 30/30A - 2003
    1. Expanded section on low melting point components for piping
    2. Requirements for dispensing hoses
    3. Requirements for delivery hoses
    4. Operating requirements from unattended self-service motor fuel dispensing facilities
3. Problems with New Fuel Additives
    1. Investigation of MTBE
    2. Preventing Phase Separation with Ethanol
    3. Biodiesel Storage and Maintenance
    4. Hazards of WD-40
    5. Highlights of the 2005 Energy Bill
4. Revisions to Steel Tank Institute Installations Instructions
    1. Allowing native soil containing rocks up to 1/2" dia.
    2. Allowing very fine backfill up to a #200 sieve
    3. Only requiring compaction of backfill up to 60% of the tank diameter
5. How to Avoid Tragidc Accidents, UST Accidents
    1. A tank containing new motor oil mysteriously exploded
    2. An underground tank used to store motor fuel aboveground almost caused the destruction of an entire town
    3. One inspector required a contractor to put dry ice in a tank and "haul it out of his district". This situation almost ended in tragedy.
    4. The two factors most responsible for fatal UST accidents
    5. Following these simple steps will avoid most tragic tank removal accidents
6. Problems with Flexible Piping
    1. Compatibility problems with gasoline
    2. Class Demonstration of an actual sample
    3. How flexible piping is constructed
    4. Permeability of Flexible Piping vs. Fiberglass Piping
7. Problems with Cathodic Protection Systems
    1. Overlooked areas where Cathodic Protection is required
    2. Improper record keeping
    3. Failure of systems with impressed current installed
    4. Improper testing procedures
    5. Confusion over metallic flex connectors in contact with the soil or water
    6. No action taken when Cathodic Protection Tests failed
8. Problems with Internal Tank Lining
    1. Study of premature failures
    2. Improper or no inspections after installation
    3. Lining contractors not following the tank liners protocol to determine if tank qualifies for lining
    4. Proper documentation by owners
9. Problems with Intersitial Monitoring
    1. Perception by operators that it never needs monitoring orf maintenance
    2. Operators not properly trained
    3. Testing the sensors
    4. Routine maintenance
    5. Proper installation of the sensors
10. Problems with Spill & Overfill Prevention
    1. Accident where 4 people burned to death sitting in their cars at a C-Store
    2. Field test to determine correct installation of overfill prevention devices
    3. Test to determine if the device is suitable for this site
    4. Inspection procedure to determine if the overfill prevention device is working correctly
    5. Do site operators know what action to take of an overfill occurs?
11. Automatic Tank Gauges
Operator not knowing how to operate equipment
    1. Sites generating the wrong reports
    2. Improper installation and start up
    3. Operators not responding to alarms
    4. Maintenance Items Checklist
12. Electronic Line Leak Detectors
Problems with manufacturers claims
    1. On-Site Testing not covered by the manufacturer
13. Problems with Statistical Inventory Reconciliation
    1. Handling inconclusive results
    2. Discussion of EPA concerns of claims made by the SIR providers
14. Precision Tightness Tests
    1. Case where Grand Jury indicts 10 people of wire fraud for falsifying Precision Tightness Tests
15. SPCC Plan Requirement for UST's
    1. When a S.P.C.C. Plan is required for UST sites?
    2. What are the requirements of an S.P.C.C. Plan?
16. PEI/RP400-200
    1. Testing for electrical continuity of Petroleum Dispensing Systems
17. Testing Compartment Tanks
    1. The chapter covers the testing procedure for testing compartment tanks
18. Suggestions for Testing Line Leak Detection using Containment Sumps
    1. Illustrates a suggested method for testing line leak detection using containment sumps with no mechanical line leak detectors.
Top of Page


"Underground Storage Tank Technician's Training Course"
Course Outline

8 Credit Hours

1. OSHA Confined Space Entry Regulations
    1. What is the difference between a confined space and a "permit-required" confined space?
    2. What are some of the "permit-required" confined spaces in the petroleum industry?
    3. What are the entry requirements for a "permit-required" confined space?
    4. When is a full "permit-required" confined space program not required?
    5. Example of a confined space permit
2. OSHA Lockout/Tagout Regulations
    1. How do these regulations apply to the petroleum industry?
    2. How to perform a lockout/tagout shutdown?
    3. Who is required to comply with lockout/tagout regulations?
    4. What equipment is needed to perform a shutdown?
3. How to Read MSDS Sheets
    1. How are MSDS sheets used at UST sites?
    2. What is contained in MSDS sheets?
    3. Who is required to have MSDS sheets?
    4. Examples of using MSDS sheets.
4. Revisions to NFPA 30A
    1. Latest NFPA 30A revisions
    2. Discussion of how these changes affect UST operators and technicians
5. Spill & Overfill Prevention Regulations
    1. What do the federal UST regulations on spill and overfill prevention require?
    2. When spill and overfill prevention is not required on UST systems
    3. Three types of overfill prevention systems allowed in the federal regulations
    4. Limitations of the different overfill prevention systems
    5. Overfill prevention installed on romote fills
    6. Recently discovered problems with Spill & Overfill Equipment
6. Lead Detection Regulations
    1. Federal UST leak detection regulations
    2. When is leak detection not required?
    3. When is a precision tightness test required?
    4. Demonstration of all of the leak detection methods recognized in the federal UST regulations
    5. Leak detection is site specific. Not all methods work at all sites
    6. What is third party certification and how does it aply to leak detection used on USTs?
    7. Problems found with interstitial monitoring
    8. Problems found with Automatic Tank Gauging
    9. Suggestions for testing line leak detectors using sensors inside containment sumps
7. Piping
    1. Federal UST regulations for underground piping
    2. What are the federal regulations for steel flex connectors and piping that comes into contact with the soil?
    3. Requirements for Emergency Shut_OFF valves
    4. Requirements for vent lines
    5. Problems found with flexible piping systems
8. Static Electricity
    1. How Static Electricity is generated
    2. Fires at service stations caused by static electricity
    3. How to prevent fires caused by static electricity
    4. How to Test Continunity on Petroleum Dispensers
9. Safety Issues for Technicians
    1. Safety Vests - Non static generating
    2. Barricades to create a safe working area
    3. Proper signing to help create a safe workplace
    4. Static electricity
    5. The hazards of WD-40
    6. Specifications for the proper Fire Extinguishers used at UST sites
    7. Minimum personal protective equipment to be worn by UST technicians
10. Monitoring Instruments
    1. Combustible Gas Indicator - when it can an cannot be used at a UST site
    2. Proper instruments to use in an oxygen deficient environment
    3. Difference between methane response vs. no methane response
    4. Oxygen Sensor
    5. Calibration
    6. Repairs
Top of Page

[Home] [Email] [Back to Training] [Expert Witness]
[Consulting/On-Site Inspections] [Equipment]